Camp Berry Work Day
WORK-DAY– April 13, 2024, Saturday, 8-4pm, Lunch provided
-
Interior rough electrical work
-
MC Cable runs to the bathrooms
-
Tie into breaker panel (Brent or under his supervision)
-
Complete slip fitter for Central Distribution center
-
Pull strings to determine length of run from Central Distribution to Shower House
-
Install underground pipes for gutter down spouts
-
Install mounts for front wall railing and after grading, ground cover under railing area
-
Check to see if any additional framing is needed
-
Install additional retaining wall block & geo grid
-
Clean out inside of shower house in preparation for final coat of pain overall
-
Service tractors, mowers and other equipment for new year – oil, grease, hydraulics, sharpening, etc.
We have other projects if we have enough people