WORK-DAY LIST – Feb 10, 2024, Saturday, 8-4pm, Lunch provided

  • Complete framing for ceiling
  • Install insulation baffles
  • Run MC Cable electrical runs to the bathrooms
  • Run vent piping
  • Put in pull strings in electrical pipes for proper lengths
  • Cut windows into 2 outside doors and adjust latch plates
  • Check for a possible leak in the drainage pipes
  • Install settings on the septic dosing pump
  • Dispose of some pallets and clean up leftover retainer cover stones and pallets
  • Weather permitting we may start setting up the stone and sidewalks around the shower house