Camp Berry Work Day
Work Day – July 20, 2024
Shower House finish Rough electric wiring
- Runs to lights to junction box then to motion sensor
- Runs to fans
- Runs to water heaters
- Install exhaust fans for the 4 bathrooms (go outside mechanical room)
- Do one run of 10” flex duct and Y 8” ducts to proper locations in closest bathroom and test
Run wire from Central Distribution Center to Showerhouse – under Brent supervision
Form up Dump Station for concrete
Lay out of propane and water
Retainer wall – initial layers
Kubota tractor – replace relay
JD 350 Trac Loader – replace starter
Entrance – create pattern in ¼” plywood, then drill holes and install holders for white plastic rails, if ground is ready, install rubber roofing