Camp Berry Work Day
Work Day – October 26, 2024
- Finish Fiberglass Ceiling and Walls
- Make access door in central hallway
- Put in ceiling and access doors in Storage and Mechanical Room (use drywall if fiberglass runs out).
- Add gray plastic strips to the long side of fiberglass sheets – -gray plastic needs to be cut – probably 1-1/2” wide
- Electrical
- Foam boxes in handicap bathrooms and put covers on
- Wire in motion sensors – in handicap bathrooms and storage and mechanical rooms – test lights and fans
- Finish dosing pump wiring
- Emergency Lights – install 4 with remote lights outside doors
- Finish large wiring – grounds, etc.
- Farm House – ring out all circuits and note on a breaker plan
- Finish sink countertops with smooth cement
- Once sink countertops are finished, apply pool paint (white or tinted?)
- Level ground around septic tanks
- Install fence
- Install rubber roofing under fence
- Install with lawn staples
- Add lawn staples to entrance rubber roofing ground cover
- Install rubber roofing and lawn staples at water slide
- Research and install plastic partitions in handicap and other bathrooms if it doesn’t interfere with painting floor
- Install grab bars in handicap bathrooms
- Add combo lock to RV pump house
- Put mouse/rat poison plastic units in farmhouse basement, shed, lower pole barn, barn basement, pump houses
- Plumbing – under Mike Ardeno direction
- Install screen on 4” exhaust vent above shower house roof
- Find missing vent pipe connection and plug (under floor)
- Install 4 water heaters
- Install supply pipe – – red for output of water heaters and blue for cold water to toilets and urinals
- Install shower heads and shut offs
- Install urinals
- Install sinks and faucets after countertops finished