Camp Berry Work Day
May 10, 2025 WORK DAY – need all hands on deck
- Shower House – call Steve for latest needs 302-379-1580
- Finish painting countertops – block filler first, then 2 part epoxy
- Install sinks & faucet system
- Sinks, toilets, divider panels, shower curtains, etc.
- Caulk any holes, and touch up with block filler and then epoxy walls in shower areas
- Install hardware for shower curtains
- Make 16 benches for shower and 4 for wall between sink and urinals
- Install curtains in the windows
- Clean up concrete on sidewalks with grinder (Steve can provide)
- Finish trim per example by Rowland Troutman
- Paint the 10 doors carefully – – green for outside and tan for inside
- Move keybox to shower house between Storage room and Handicap bathroom
- Install 4 thermostats and wire to space heaters
- Install gas flex pipe from black pipe to space and water heaters
- Install Split Rail Fence around septic tanks, above retaining wall (after septic field is in)
- Grind floor and acid wash
- Paint floor – & insulate attic – Rowland is arranging for that
- Install toilets – when Mike Ardeno is ready
- Install urinals – when Mike Ardeno is ready
- Ground cover at top of water slide area needs to be done with rubber roofing