Camp Berry Work Day
June 14, 2025 WORK DAY – need all hands on deck arrive ~ 8-8:30, we will provide lunch (or come on a day when you can and check with Steve what needs to be done)
- Maintenance – change oil, filters on tractors, check coolant, etc., grease (contact Wyatt Garrett if you can help)
- Prep for Adventure Weekend and JLDA
- All bricks moved from covered area near store and by main pavilion (move to back and organize can move block closer to blacksmith shop but out of way of digging footer)
- Weed wack any areas not being mowed that should be cut down for Adventure Weekend
- Move Shooting sports shed when site work done on other side of road
- Organize lower pole barn and put rubber roofing in, fold up sections that were drying and put on pallet to go to pole barn, put small pallet on top of full pallet and keep ground staples with rubber roofing
- Get rid of old large farm trailer unless someone wants to fix it
- Fix the broken picnic table (seat) and organize tables in the main pavilion (trac loader and JD Tractor will move out during Adv Wknd -can cover on trac loader exhaust pipe)
- Someone can take a box of metal in main pavilion to scrap yard for a few bucks
- Shower House – call Steve for latest needs 302-379-1580
- Consolidate Fiberglass panels and move to back side of shower house – side toward farmhouse, get rid of pallets
- Finish ceilings in storage, mechanical and handicap bathrooms & trim per example by Rowland Troutman
- Install 2 motion sensors and lights once ceiling panels installed in storage and mechanical room
- Move interior panels and spread out across the back side of the shower house so we can select ones to be used for different areas
- Install faucet system, connect drains
- Install Shower curtain rods, hooks in shower area
- Finish any defects in floor before final sanding and application of epoxy
- Make 16 benches for showers (Tim Fichtner manufacturing final 15)
- Install curtains in the windows
- Clean up concrete on sidewalks with grinder (Steve can provide)
- Paint the 10 doors carefully – – green for outside and tan for inside
- Install gas flex pipe from black pipe to space and water heaters
- Install Split Rail Fence around septic tanks, above retaining wall (after septic field is in)
- Grind floor and epoxy floor – Rowland has contact
- Insulate attic – Rowland is arranging for that
- Install toilets – after floor coating is done
- Ground cover at top of water slide area needs to be done with rubber roofing