WORKDAY LIST – Saturday, July 15, 2023
- Shower House – Lag Bolts and top plates on certain walls
 - Shower House – Finish framing for ceiling and upper walls
 - Shower House – Clean floor, Grind floor where needed and final clean
 - Shower House – Touch up wall seams or other areas prior to painting
 - Shower House – Finish framing for ceiling and upper walls
 - Shower House – Excavation – Andy will come and we will put 6” pipe from shower house across road
 - Shower House – Move hollow extra hollow block to back of property
 - Shower House – Vent pipe tie together and exhaust
 - Shower House – Plan exhaust for propane water heaters
 - Glue retaining wall end and cap blocks – all cap blocks have been put at the top next to the wall
 - Install air conditioner in Barn Meeting room with proper support – for use by JLDA
 - Clean up Farm House basement
 