Camp Berrry Work Day
- Re-install 6” pipe across driveway to new tank location
- Grade around entrance wall and columns
- Install 3” pipe from pole to Central Service panel
- Move hollow Block from shower house to store near lower Pole Barn
- Move 2350 12” bricks to front near un built wall, few for finishing other wall.
- Paint Plywood on Central Service Panel and seal top and bottom between sides
- Paint trim in kitchen
- Patch walls in shower house
- Move a few more items out of shower house getting ready for painting
- Organize materials in lower barn
- Fix universal on 8’ mowing deck
- Tighten several hydraulic hose fittings on John Deere Tractor
- Move wood stored on Farm House back porch inside